Recent News

  • Public Information Center: Early Spring, Location TBD
  • French & Parrello Associates has completed a Phase 1 visual inspection of the wall to assess its condition and locate structural deficiencies. The inspection was completed over the course of 5 days between the dates of Monday, May 21 and Friday, May 25, 2018.
  • Techniquest has completed manual and automatic traffic counts along Manhattan Avenue, Palisade Avenue and at the intersections adjacent to the Project area. This was completed as part of the ongoing traffic study which will help determine available detour routes for future construction work.
  • Advanced Infrastructure Design (AID) has completed the Ground Penetrating Radar (GPR) scans during the week of Monday, May 21, 2018. This information will help determine the structural composition of the wall and detect voids behind the wall.
  • SkyGear Solutions has completed the first round of Thermal Infrared (IR) scans of the wall on Tuesday April 24, 2018. This information will help monitor rainwater drainage from behind the wall.
  • The first Local Officials Meeting took place on Tuesday, April 17 at 1:00pm.
  • GEOD Corporation completed the aerial survey of the wall and is preparing basemap drawings which will be used as part of the future repair plans.
  • GEOD Corporation completed the Terrestrial Laser Scan of the wall on December 28, 2017.
  • Bartlett Tree Experts finished clearing vegetation from the wall on December 12, 2017.
  • French & Parrello Associates gathered and reviewed available documentation, including plans from 1906, 1912 and 1914; previous repair plans; reports, historic photos of the site and wall; etc.
  • Community input and comments are always welcome during this study. Members of the public are encouraged to visit the webpage regularly to view our progress or to sign up for the email list to be notified of events and future public meetings.