Week 1, 7/22

  • Mobilize Rig
  • Perform S2, estimated 2 days
  • Perform site clearing/prep for S4 to S6, estimated 2 days   

Week 2, 7/29

  • Mobilize Rig 
  • Perform S1, estimated 2 days 
  • Perform S3, estimated 2 to 3 days
  • Mobilize to S4/S5 

Week 3, 8/5

  • Perform S4, estimated 2 to 3 days 
  • Perform S5, estimated 3 days 
  • Mobilize to S6

Week 4, 8/12

  • Perform S6, estimated 2 to 3 days
  • Mobilize to N1
  • Perform N1, estimated 2 to 3 days 

Week 5, 8/19

  • Mobilize to N2/N3
  • Perform N2, estimated 2 days 
  • Perform N3, estimated 2 days 

Dates/Week of activities below are TBD.

  • Return to all borings to perform ATV/OTV logging, estimated 2 days.
  • Return to S3, S5, & N2 for double packer tests, estimated 2 days. 